Dean H. Stanton · Selected Work

Environmental Stress Screening Buildout & Connector Reliability Improvement

Built and supervised an environmental stress-screening function and led a connector-reliability improvement that reduced environmental-test failures.

Results

Results and contributions.

01>75%Connector-related environmental-test failures fell by more than 75%, as reported in historical records.
02Tens of thousandsThe connector-reliability correction was reported to save tens of thousands of dollars.
01
Situation

Operating context

A growing defense-electronics operation needed a formal environmental-screening capability and a disciplined response to a recurring connector-related failure pattern exposed during environmental testing.

02
Challenge

What made the work difficult

The work had to balance production shipment needs with constrained test capacity and equipment readiness while preserving technical controls and separating interacting failure mechanisms from simplistic root-cause assumptions.

03
Dean's role

Responsibility and authority

Dean established and supervised the ESS department, including personnel, procedures, scheduling, equipment operations, computerized records, and test support. He also led connector failure analysis, corrective action, training, verification, and implementation.

04
Actions

How the work moved forward

  1. Built the formal ESS department, procedures, equipment controls, scheduling, and computerized test-record system.
  2. Established yield and failed-test-location tracking to support production and reliability decisions.
  3. Analyzed the connector failure pattern across environmental conditions, assembly and workmanship, and component behavior.
  4. Implemented corrective actions, revised procedures and work instructions, trained personnel, and verified effectiveness.