01$51MLed production engineering on the $51 million MK 41 Vertical Launching System program.
027 bindersCompleted a seven-binder Motorola NRE validation package covering manufacturing work instructions, process flow, work aids, shop orders, an indentured BOM, tooling, and floor validation.
03Several hundred hoursHistorical project summaries report several hundred labor hours and tens of thousands of dollars saved through digital work instructions.
04Thousands of hoursBroader improvements combining digital work instructions and other work aids were reported to save thousands of manufacturing labor hours.

This broader measure includes work-instruction improvements and should not be added to the narrower result.

01
Situation

Operating context

A defense manufacturer needed to sustain complex production, recover customer-facing execution, and replace a legacy production and inventory system before Y2K-related continuity and data risks became critical.

02
Challenge

What made the work difficult

The transition had to proceed inside live defense production with strict configuration, quality, traceability, documentation, data-migration, training, and adoption requirements.

03
Dean's role

Responsibility and authority

Dean managed a five-engineer product and manufacturing engineering group supporting two facilities. He led production engineering, facilitated legacy-system replacement and Visual Manufacturing implementation teams, developed schedules, and coordinated vendors, hardware, migration, pilots, training, manufacturing documentation, and process controls. Final ERP approval and vendor delivery were shared responsibilities.

04
Actions

How the work moved forward

  1. Managed product and manufacturing engineering across two defense-production facilities.
  2. Led production engineering support on the MK 41 Vertical Launching System program and related customer-facing defense work.
  3. Facilitated the legacy PICS replacement and Visual Manufacturing implementation program, including vendor evaluation, schedules, hardware, data conversion, pilots, training, and manufacturing controls.
  4. Produced and coordinated controlled manufacturing documentation, configuration, tooling, calibration, digital work-instruction, and work-aid systems.